Is there anyone who can assist/volunteer with drawings/plans for proposed field upgrades?

Any assistance with these areas we will promote/advertise your company.

  1. Install additional lights ASAP – We cannot start working on items 3-8 until these trucks have done their job.
    (We have this donated but need a couple of weeks of dry weather for trucks to be able to work on the fields)

  2. Grade swampy area ASAP – We estimate this will take about 200 tons of dirt, and again, these tractors need to be finished before starting the remaining work.
    (We possibly have dirt donated and trucks to deliver, waiting on confirmation)

  3. Install irrigation from existing water meter by April 19th
    (St. Andrew P&P has the pipe to make the main run to the fields, as well as the irrigations plans. We will need assistance in running pipe)

  4. Aerate and top-dress with 120-200 tons of pure sand by May 1st.
    (We need sand?)

  5. Apply 4-5 applications of herbicides from April through May.
    (St. Andrews P&P will apply herbicide. We need herbicide?)

  6. Over-seed with 400 pounds of Bermuda grass by June 1st.
    (St. Andrews P&P will apply seed. We need grass seed?)

  7. Apply four applications of fertilizers now through August 1st.
    (St. Andrews P&P will apply fertilizer. We need fertilizer?)

  8. Allow fields to rest between June 1st and August 1st.
    (Phew, rest :-)


Go UNITED!!!